The Dryden Street ProjectNottingham, NG1.
A full turnkey refurbishment of an 80 sqm 3-bedroom flat in Nottingham — reconfigured internally, reset from top to bottom, and delivered clean and rent-ready end-to-end by Carrington.

A tired 80 sqm flat — reconfigured and reset to let-ready.
The landlord wanted to reposition the property to attract long-term professional tenants on the private market — not a patch job, but a full refurbishment including internal layout changes that would command a stronger rent and lift long-term value.
One point of contact, one price, one programme, and a clean, finished flat they could hand straight to letting agents.
BeforeOne instruction. Delivered end-to-end.
A single programme, one point of contact, and a handover-ready flat — everything coordinated by Carrington.
Complete strip-out and refit across the 80 sqm flat — including internal layout changes to reconfigure the space for letting.
New kitchen and bathrooms, tiling, sanitaryware and finishes specified for durability and rent-ready appeal.
Plastering, decoration, flooring, doors, lighting and associated M&E — delivered clean and handover-ready.
Sequenced end-to-end.
- 1Week 1Survey & strip-out
Site set-up, protection, demolition and haul-away — clearing the flat for reconfiguration.
- 2Week 2Layout & first fix
Internal layout changes built out; plumbing and electrical first fix to suit the new plan.
- 3Week 3Plaster & kitchens
Walls skimmed, kitchen installed and tiling begun across wet areas.
- 4Week 4Bathrooms & finishes
Sanitaryware and second fix completed; flooring, doors and decoration underway.
- 5Week 5Decoration & detail
Final decoration, lighting, snagging and a full clean to rent-ready standard.
- 6HandoverSnag & let-ready
Snag walk, final clean and rent-ready handover — let within 4 weeks on the private market.
Before & after — room by room.
Full room-by-room walkthrough — every space taken from tired to rent-ready.




















Every room, handover-quality.
Click any image to view the full gallery.
Reconfiguring the layout inside a tight 4–5 week programme.
The brief called for internal layout changes — reworking walls and room flow across an 80 sqm flat — which pushed first-fix M&E behind the original sequence and threatened the 4–5 week deadline.
Carrington re-sequenced the programme around the new layout — overlapping strip-out, first fix and plastering trades so the reconfiguration happened without losing the critical path, keeping the flat on budget and let-ready on time.